Contractor sues Liberty Mutual over denied bond on Detroit school demolition


Dore says it mobilized in February 2025 and, by early June 2025, had completed “approximately 95% of the physical demolition,” with the remaining work “primarily below grade.” Despite that, MIG/Rockford allegedly terminated Dore’s contract on June 6, 2025, citing nonperformance while, the filing claims, denying schedule relief for excusable delays and at the same time requiring acceleration of the work. 